单选题:预算定额消耗的编制方法中,其他用工是辅助基本用工消耗的工日,其不包括(  )。

  • 题目分类:建设工程计价
  • 题目类型:单选题
  • 号外号外:注册会员即送体验阅读点!
题目内容:
预算定额消耗的编制方法中,其他用工是辅助基本用工消耗的工日,其不包括(  )。 A.超运距用工
B.按劳动定额规定应增(减)计算的用工量
C.辅助用工
D.人工幅度差用工

参考答案:【答案仅供学习,请勿对照自行用药等】
答案解析:

Everyone, men and women, old and young ______ sports and ga

Everyone, men and women, old and young ______ sports and games. A.is enjoy B.w

查看答案

Thousands of tons of rubbish ________ over a large period o

Thousands of tons of rubbish ________ over a large period of time. A.rots away

查看答案

某施工机械耐用总台班为800台班,大修周期数为4,每次大修理费用为1200元,则该机械的台班大修理费为(  )元。

某施工机械耐用总台班为800台班,大修周期数为4,每次大修理费用为1200元,则该机械的台班大修理费为(  )元。A.7.5 B.6.0 C.4.5 D.3.0

查看答案

Bob said he was going to join our club but he didn't. He __

Bob said he was going to join our club but he didn't. He ____ his mind. A.can't

查看答案

某工程现场采用斗容量为0.5m3的挖掘机挖土,每一次循环中,挖土提升斗臂、回转斗臂、卸土、反转斗臂并落下土斗四个组成部分

某工程现场采用斗容量为0.5m3的挖掘机挖土,每一次循环中,挖土提升斗臂、回转斗臂、卸土、反转斗臂并落下土斗四个组成部分的时间分别为25s、15s、10s和15

查看答案