单选题:吊桥的主缆施工各道工序为:①猫道架设②牵引系统架设③主缆架设④紧缆⑤索夹安装与吊索架设,各工序的正确顺序为( )。

  • 题目分类:公路工程
  • 题目类型:单选题
  • 号外号外:注册会员即送体验阅读点!
题目内容:
吊桥的主缆施工各道工序为:①猫道架设②牵引系统架设③主缆架设④紧缆⑤索夹安装与吊索架设,各工序的正确顺序为( )。 A.①→②→③→④→⑤
B.②→①→③→④→⑤
C.①→②→④→③→⑤
D.②→①→④→③→⑤

参考答案:
答案解析: