Schedule development can require the review and revision of duration estimates and resource estimates to create an approved ( ) that can serve as a baseline to track progress.
A.scope statement
B.activity list
C.project charter
D.project schedule
参考答案:【答案仅供学习,请勿对照自行用药等】
答案解析: