单选题:某工程网络计划中,工作N最早完成时间为第13天,持续时间为5天。该工作有三项紧后工作,它们的最早开始时间分别为第23天、

  • 题目分类:建设工程项目管理
  • 题目类型:单选题
  • 号外号外:关注公众号送1000体验阅读点!
题目内容:
某工程网络计划中,工作N最早完成时间为第13天,持续时间为5天。该工作有三项紧后工作,它们的最早开始时间分别为第23天、第25天和第22天,则工作N的自由时差为()天。 A.4
B.9
C.7
D.10
关注公众号,送1000阅读点
关注公众号,送1000阅读点
1:点击图片或者扫二维码进入公众号,关注公众号!
2:私信发送您在66题库注册的会员号!
3:在一个小时内,您将收到充值卡
4:到点卡充值输入充值卡内容即可!
5:多关注多得!免费的呦!只要本站不倒闭,永久有效!
参考答案:【答案仅供学习,请勿对照自行用药等】
答案解析:

When students are doing activities, the teacher walks around

When students are doing activities, the teacher walks around and provides help i

查看答案

There are some speaking activities. Which of the following m

There are some speaking activities. Which of the following mainly focuses on the

查看答案

When a teacher leads students to guess the meaning of a new

When a teacher leads students to guess the meaning of a new word based on the co

查看答案

In which of the following sentences does liaison of sound ap

In which of the following sentences does liaison of sound appear most?A.Ms. Blac

查看答案

课堂提问的问题类型有哪些?举例说明其中的两种(5分)。课堂提问应遵循哪些原则(7分)?指出课堂提问的两个作用(8分)。

课堂提问的问题类型有哪些?举例说明其中的两种(5分)。课堂提问应遵循哪些原则(7分)?指出课堂提问的两个作用(8分)。

查看答案