The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date