题目内容:
The following diagram denotes dependency between two activities A and B. It says ( )。
A.B can’t start before A is finishied
B.B can’t finish before A is finished
C.B can’t start before A starts
D.B can’t finish before A start
参考答案:【答案仅供学习,请勿对照自行用药等】
答案解析: