题目内容:
The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.( ) could provide the fund to cover the newly discovered work item.
A.Contingency reserve
B.Project profit
C.Management reserve
D.Special fund
参考答案:【答案仅供学习,请勿对照自行用药等】
答案解析: