题目内容:
Each box is an activity;the number it contains is the duration of the activity in days.The duration of the critical path is.
A.16 days
B.14 days
C.19 days
D.20 days
参考答案:
答案解析:
Each box is an activity;the number it contains is the duration of the activity in days.The duration of the critical path is.
A.16 days
B.14 days
C.19 days
D.20 days